What MasterFormat is
MasterFormat is a standard published by the Construction Specifications Institute (CSI) and Construction Specifications Canada (CSC). It organizes a project's specifications, and much of its project information, into numbered divisions so the same kind of work is always found in the same place.
The 2018 edition uses divisions numbered 00 to 49. Several numbers are reserved for future use, and CSI asks users not to assign work to them. Division 00 covers procurement and contracting requirements, and Division 01 covers general requirements. Divisions 02 to 14 cover facility construction, Divisions 21 to 28 cover facility services, Divisions 31 to 35 cover site and infrastructure, and Divisions 40 to 48 cover process equipment.
How the numbers are built
A MasterFormat number has up to six digits, written in pairs. The first pair is the division. The second pair narrows the work to a subgroup or level 2 group. The third pair identifies the section. Some sections are split further with a decimal, for example 09 65 13.13 for resilient base within the resilient base and accessories section.
So 09 29 00 is division 09 (Finishes), group 29, section 00: Gypsum Board. A takeoff line that carries 09 29 00 can be found in the drywall section of the spec without searching the whole book.
The divisions that matter for takeoffs
Most takeoff work falls into a handful of divisions. The table lists the ones that come up on almost every project, with the kind of work they hold.
| Division | Title | Typical takeoff work |
|---|---|---|
| 03 | Concrete | Footings, slabs, walls, reinforcing, forming |
| 04 | Masonry | Block, brick, and stone walls and their reinforcing |
| 05 | Metals | Structural steel, metal framing, metal railings |
| 06 | Wood, Plastics, and Composites | Framing lumber, sheathing, decking, cabinets, millwork |
| 07 | Thermal and Moisture Protection | Insulation, roofing, waterproofing, sealants |
| 08 | Openings | Doors, frames, windows, hardware |
| 09 | Finishes | Gypsum board, metal framing, flooring, painting, wall coverings |
| 10 | Specialties | Toilet accessories, signage, fire extinguishers |
| 12 | Furnishings | Countertops, casework, window treatments |
| 21 | Fire Suppression | Sprinkler piping and heads |
| 22 | Plumbing | Water and waste piping, fixtures, water heaters |
| 23 | Heating, Ventilating, and Air Conditioning | Ductwork, diffusers, equipment, controls |
| 26 | Electrical | Conductors, raceway, panels, devices, lighting |
| 27 | Communications | Data and voice cabling, audio-visual |
| 28 | Electronic Safety and Security | Fire alarm, access control, video surveillance |
| 31 | Earthwork | Excavation, backfill, grading |
| 32 | Exterior Improvements | Paving, site concrete, fencing, landscaping |
| 33 | Utilities | Site water, sewer, and storm lines |
Trade scope and division are not the same thing
A subcontractor prices a trade, not a division. Drywall work, for example, spans wall blocking in Division 06, insulation in Division 07, and board, studs, and finishes in Division 09. A takeoff organized only by division puts the drywall package in four places, and a takeoff organized only by trade loses the spec reference.
Good takeoffs keep both. Each line is grouped by the trade that prices it and carries the MasterFormat code that files it in the spec. That is how a schedule can be checked against the project manual and still be ordered from directly.
Check the edition before you rely on a code
MasterFormat has been revised several times since 2004, and numbers move between editions. A section that is 09 21 16 in one edition may be filed somewhere else in another. The edition named in the project manual governs, so check the codes against it before you use them.
The most reliable source is the project's own table of contents. If a section is listed there, that scope is specified. If a section is not listed, the scope may be elsewhere in the set or may not be in the project at all.
A practical checklist
- Pull the project manual table of contents and note the edition it uses.
- List each trade scope you are pricing and the divisions it touches.
- Map each scope to its sections, and mark any section marked by others or not in the set.
- Check the drawings for the same scope against the spec, and flag any difference rather than choosing one.
- Keep the code on every takeoff line so the schedule can be filed against the spec without re-reading the book.