What a drywall takeoff covers
A complete drywall takeoff covers gypsum board on walls and ceilings, the metal studs and track that frame the walls, insulation in the walls and ceilings, and the accessories that finish the edges and joints. Soffits, bulkheads, and shaft walls are usually counted as their own items, because they are framed and boarded differently from a standard partition.
Start with the wall type legend
Before you measure anything, list every partition type on the plans. Each type should define the board layers and thickness, the stud depth and gauge, the stud spacing, the insulation, and any fire rating. If a type is not defined on a legend sheet, flag it rather than guessing.
Measuring by wall type keeps a 1-hour partition from being priced as a 2-hour partition, and it lets each board and stud line be ordered as a single product.
Measure wall area
Wall area is the length of each wall multiplied by its height, less the openings. Length comes from the floor plan, and height comes from the wall section or the elevation. A wall that runs to the structure above is measured to the deck height shown on the section, not to the finished ceiling.
Net out doors, windows, and pass-throughs only where the drawings dimension them. An opening without a dimension should be flagged, because a rough estimate of its size changes the sheet count.
Measure ceilings and soffits
Ceiling area is measured from the reflected ceiling plan, not the floor plan, because ceilings are often a different shape from the room below. Soffits, bulkheads, and sloped ceilings are separate lines. A sloped ceiling is measured along the slope, not its flat footprint.
Count the board
Divide the net area by the area of one sheet, then round up. The common sheet sizes are 4 by 8 feet, which is 32 square feet, and 4 by 12 feet, which is 48 square feet. Choose the sheet size that fits the wall height and the layout you expect.
For example, a wall run of 360 square feet on 4 by 8 sheets needs 360 divided by 32, which is 11.25, so 12 sheets before waste. Waste depends on the layout, the number of openings, and how the installer cuts the board, so add it according to your installer's practice rather than a fixed percentage.
Published estimating guides commonly cite a board waste allowance of about 10 to 15 percent, higher for layouts with many cuts, soffits, and small rooms. Confirm the allowance with your installer, because it is their cutting pattern and crew habits that set the real number.
Count the studs
Studs at 16 inches on center are spaced 1.33 feet apart, so a wall of a given length needs its length divided by 1.33 plus one stud at the end. In practice that is the length in feet multiplied by 0.75, plus one.
For a 40 foot wall at 16 inches on center, that is 40 times 0.75, which is 30, plus one, so 31 studs. Add extra studs at corners, at each side of an opening, and at intersections, because the framing detail usually calls for them. Spacing that is not 16 inches changes the multiplier, so use the spacing on the wall type.
Maximum framing spacing also depends on how the board is applied. Board run parallel to the studs is typically limited to 16 inches on center, while board run perpendicular to the studs may go to 24 inches on center. Use the spacing and orientation shown on the wall type, and check the manufacturer's installation guide.
Count the track
Top and bottom track runs along the same wall lines as the studs. For a wall with no openings, the track is roughly twice the wall length. Subtract the track that stops at each door, and add track for any header or sill that the framing detail requires.
Measure insulation and accessories
Insulation is measured by the area of the wall or ceiling it fills, not the board area, because the board and the insulation are often different on the same wall. Use the thickness and the rating from the wall type.
Corner bead and control joints are measured by length along the corners and joint lines. Joint compound and tape are usually priced by the board area, and the rate depends on your finish level and your crew, so confirm that rule with your estimator before you apply it.
Mistakes that cause short orders
- Shaft and rated walls priced as standard partitions, so the board layers and fire rating are wrong.
- Ceiling board missed because the count only used the floor plan.
- Openings that were not netted, or netted when the drawings did not dimension them.
- Studs counted at the nominal spacing when the wall type calls for a closer spacing or a deeper stud.
- Track counted for the full wall length when doors stop it, which overstates the order.
- Wall height taken from the finished ceiling when the wall runs to the deck above.
Drawings to request
- Floor plans with every partition type tagged.
- Reflected ceiling plans, so ceiling board and soffits are counted from the right drawing.
- The wall type legend or partition schedule.
- Wall sections and details for shaft, rated, and high walls.
- Door and window schedules, so openings are netted out correctly.